Aluminum Casting Lead Time: Tooling to Production
At Bohua, drawing confirmation to first article takes 5–6 weeks. That milestone is separate from sample approval and production delivery. Plan those later dates around the agreed machining, inspection, correction, and buyer approval requirements. A useful schedule names the starting revision, the evidence required at each stage, and the person responsible for release.
On this page
What the 5–6 weeks cover
The confirmed Bohua interval runs from drawing confirmation to first article. Agree production delivery separately after defining sample approval and release requirements.
At Bohua
Bohua designs and makes molds in-house. Drawing confirmation to first article takes 5–6 weeks. The mold workshop has 17 machines. Casting, core making, tooling, T5/T6 heat treatment, CNC machining, and inspection are on the same site of about 16,300 m².
Before accepting a schedule, record what condition the first article must be in. An as-cast part, a heat-treated part, and a fully machined part are different deliverables. List the accompanying records separately. Agree which approval records accompany the first article and which follow at later milestones.
For the manufacturing scope behind this schedule, see Bohua's gravity casting capabilities. Use the gravity casting tooling guide to define the tooling scope before release.

At Bohua
Bohua uses UG and SolidWorks for mold design before the first-article milestone.
Casting simulation for that tooling work uses AnyCasting.
Set drawing release and tooling-review decisions in the schedule alongside the required first-article condition.
Separate first article, sample approval, and production delivery
Give each milestone its own output and release decision. The following table is a planning checklist, not a set of standard durations.
| Milestone | Buyer input or decision | Output to agree | Risk to resolve |
|---|---|---|---|
| Drawing confirmation | Released drawing and model; material; critical features | One agreed revision and manufacturing scope | Conflicting files or unresolved design changes |
| Tooling preparation | Tool concept approval and change authority | Mold, core tooling, and fixture scope; progress checkpoints | Late changes to geometry, cores, or machining datums |
| First article | Sample quantity and required delivery condition | Initial parts and agreed inspection findings | Incomplete filling, dimensional issues, or inadequate machining stock |
| Correction and sample approval | Consolidated comments and an approval owner | Disposition of findings; revised parts and records where needed | Tool changes, heat-treatment distortion, or failure at a machined sealing face |
| Production release | Accepted sample evidence and required production controls | Written release and agreed recurring inspection scope | Missing approval or unresolved functional requirements |
| Shipment and delivery | Release quantity, packaging, destination, and freight basis | Separate dispatch and arrival milestones | Unagreed packaging or transport assumptions |
Show dependencies explicitly. A machining fixture may depend on the approved datum scheme. Sample approval may depend on a report or a buyer's assembly test. Record who owns each dependency before treating a requested date as an agreed date.
Ask whether the quoted schedule already includes a correction loop after the first article is measured. Changing datums, an undefined surface requirement, or an inspection method added after tooling release usually moves the date more than the casting cycle. Do not treat the first article as accepted until the agreed evidence has been reviewed.
At Bohua
Development of an A356 pump volute at Bohua took more than a year and included several revisions to the mold and risers.
Use this pump-volute development case when discussing correction and validation milestones; agree the development schedule for your own part separately from the first-article interval.
Define what the first sample must prove
A sample should answer a defined engineering question before it advances the schedule.
A fit model can check assembly space without proving the casting route. A production-intent sample needs a record of any differences from planned production: tooling, alloy, heat treatment, cores, machining, and finishing. Identify the validation still needed for those differences.
- Define the delivered condition. State whether the sample is as-cast, heat-treated, machined, or finished. Identify sealing faces, bores, mounting locations, and surfaces that need machining stock.
- Agree the evidence. Specify dimensional, material, internal-quality, or functional records where required. Define inspection coverage and acceptance criteria before samples are made.
- Assign approval. Name the owner of component checks, assembly checks, and the final release. Record acceptance, rejection, or a request for correction against the same revision.
- Control corrections. Keep one ranked issue list. For each change, identify the affected tool or process, the next sample requirement, and the schedule impact.
At Bohua
Inspection equipment includes CMM and X-ray systems. PPAP support is available up to Level 5. Specify the tests and documents required for your order in the RFQ so we can review the approval package with the manufacturing scope.
See Bohua's inspection capabilities for the available equipment. For a suspension bracket, use the automotive suspension bracket RFQ requirements to identify the application-specific inputs.

Remove missing inputs before tooling starts
A stable revision and a complete scope make the milestone plan usable.
- Technical files: provide matching 2D drawings and a 3D model. Identify open design decisions and the person authorized to close them.
- Material and processing: state alloy, heat-treatment condition, machining datums, finish, and required functional checks.
- Demand: separate sample quantity, first production release, and annual demand. Give a forecast range if demand is uncertain. State whether releases are regular, seasonal, or one-time.
- Tooling responsibility: agree ownership, modification approval, maintenance, storage, and transfer arrangements. Do not assume these terms from a sample date.
- Delivery: distinguish the date parts must leave the plant from the date they must reach the destination. Include packaging and freight assumptions.
For a multi-part program, give a separate demand range and release pattern for each item. Identify which quantities depend on customer approval. Changes to volume, drawing revision, material, or inspection scope should trigger a review of the affected milestones.
At Bohua, orders are quoted by annual volume; small batches negotiable. See the small-batch casting RFQ guide for quantity planning.
Use the casting drawing requirements to organize the technical package, then send it through Request Quote with separate first-article, approval, and delivery targets.
Send your drawing and required milestones
Include the drawing revision, sample needs, annual volume, approval requirements, and destination. Not sure which process fits? Tell us what the part must do. In a free drawing review, our engineers recommend a process and suggest design changes where needed.
Send your drawing →